SUNY Fredonia Mason Hall Chilled Water Line Expansion

Fredonia, NY

Project Objective

The goal of this project was to extend an existing 4” chilled water line for the SUNY Fredonia music education building (Mason Hall).

Unique Project Features

Though the building is not currently air conditioned, the design included calculations to ensure that the cooling capacity of the new lines is adequate for the future planned installation of air conditioning.

Encorus Group Solution

Encorus designed an extension of the existing 4” chilled water line, taking into account the client’s desire to install air conditioning in the building at some point in the future.

Specific Project Tasks

  • Preparation of drawings for use in bidding and construction
  • Calculations to incorporate adequate capacity for future air conditioning system installation
  • Preparation of cost estimates
  • Review of bids received